Project plan

A dependency-led task plan from the first project brief through City approval, final cost agreement, permit issuance, and the builder’s notice to proceed.

Blocked by identifies the task that must finish before the next one can start. Each row has one accountable owner and one tangible deliverable.

Project foundation

IDTaskAccountableDeliverableBlocked byStatus
P01Write the design brief.OwnerGoals, non-negotiables, requested work, exclusions.—Not started
P02Set the target budget.OwnerMaximum all-in budget; separate preconstruction and construction contingency.P01Not started
P03Assemble the property record.OwnerPlans, permits, City records, photographs, prior correspondence, known defects.P02Not started
P04Engage the architect.OwnerSigned agreement defining design, coordination, submission, and construction-administration scope.P03Not started

Existing conditions and historic direction

IDTaskAccountableDeliverableBlocked byStatus
B01Measure and document the house.ArchitectMeasured as-built plan; floor elevations; roof, window, skylight, and utility record.P04Not started
B02Identify construction risks.ArchitectExisting-condition risk log: floor, roof, framing, plumbing, electrical, and access.B01Not started
B03Engage an independent historian.OwnerLimited engagement for evidence and fabric review; no City-side conflict.B02Not started
B04Establish the historic baseline.HistorianInventory of original, altered, missing, uncertain, and character-defining elements.B03Not started
B05Choose the historic strategy.OwnerWritten direction: pursue removal, design for consistency, or keep both options open.B04Not started

Concept and budget test

IDTaskAccountableDeliverableBlocked byStatus
C01Develop design options.ArchitectSchematic plans and exterior approach for the preferred suite, bathroom, roof, windows, skylights, and additions.B05Not started
C02Select a preferred concept.OwnerOne concept authorized for review.C01Not started
C03Review the preferred concept.HistorianHistoric-impact memo identifying constraints, risks, and recommended changes.C02Not started
C04Revise the concept.ArchitectOne coordinated, historically informed schematic plan.C03Not started
C05Engage builder for preconstruction.OwnerBuilder preconstruction agreement or written pricing scope.C04Not started
C06Complete builder site walk.BuilderConstructability log, site-access notes, utility concerns, and missing-information list.C05Not started
C07Prepare preliminary cost plan.BuilderEarly line-item budget, allowances, exclusions, contingency, and schedule range.C06Not started
C08Accept, reduce, or revise scope to budget.OwnerWritten budget decision and authorization to proceed.C07Not started

Permit design and City submission

IDTaskAccountableDeliverableBlocked byStatus
D01Make major owner selections.OwnerFixture direction; window, skylight, roof, door, and finish budget decisions.C08Not started
D02Define consultant scopes.ArchitectStructural, plumbing, electrical, energy, and other consultant requirements.D01Not started
D03Develop permit-ready drawings.ArchitectPlans, elevations, sections, site plan, roof/skylight details, window details, and specifications.D02Not started
D04Prepare historic submittal material.HistorianHistoric analysis, consistency input, or peer-review material required for the chosen path.D03Not started
D05Review the permit-ready set.BuilderConstructability review, revised estimate, and unresolved-items register.D03Not started
D06Resolve design, historic, and cost gaps.ArchitectOne coordinated City-submittal set.D04, D05Not started
D07Authorize submission.OwnerSigned application authorization and approved fee exposure.D06Not started
D08Submit the City package.ArchitectComplete Design Study, planning, historic, and permit application package.D07Not started

City review and final cost

IDTaskAccountableDeliverableBlocked byStatus
E01Receive completeness comments.CityCompleteness determination and comment list.D08Not started
E02Respond to planning and technical comments.ArchitectRevised plans and written responses.E01Not started
E03Respond to historic comments.HistorianResponse memo or revised historic material, if required.E01Not started
E04Resubmit the coordinated package.ArchitectFinal revised City package.E02, E03Not started
E05Receive planning and historic decision.CityApproval, conditions, or a new revision request.E04Not started
E06Incorporate approval conditions.ArchitectApproved-for-permit / construction drawing set.E05Not started
E07Perform final builder takeoff.BuilderFinal itemized proposal based on the approved scope.E06Not started
E08Lock selections and allowances.OwnerSigned selection schedule and accepted allowances.E07Not started
E09Issue final contract proposal.BuilderFixed price or GMP, schedule, payment schedule, exclusions, contingency, and change-order rules.E08Not started
E10Approve and sign construction contract.Owner + BuilderExecuted construction agreement.E09Not started

Ready to mobilize

IDTaskAccountableDeliverableBlocked byStatus
F01Obtain the building permit.Architect / BuilderIssued building permit and approved construction documents.E06, E10Not started
F02Prepare to mobilize.BuilderSite-protection plan, insurance, procurement schedule, subcontractor plan, and start date.F01Not started
F03Issue notice to proceed.OwnerWritten authorization for the builder to begin work.F02Not started